Bid Results: Job No. 09-2520
| Project Name: |
Central Watershed Sewer Relief Line (CO-1) Phase I (Rehabilitation) |
| Closing Date: |
September 23, 2009 |
| Est. Cost: |
$4,863,900.00 |
|
| Documents are in Adobe Acrobat PDF format. |
|
|
|
|
Unofficial/Untabulated Bid results as follows:
|
Bidder Info
|
Bid Amount
|
|
|
RePipe Construction, Ltd.
7600 S. Santa Fe, Bldg. E
Houston, TX 77061
|
$2,919,435.00
|
|
|
|
|
|
Bidder Info
|
Bid Amount
|
|
|
Insituform Technologies, Inc.
8121 Broadway, Suite 300
Houston, TX 77061
|
$3,820,385.00
|
|
|
|
|
|
Bidder Info
|
Bid Amount
|
|
|
Reynolds Inliner, LLC
4701 Decker
Baytown, TX 77520
|
$3,864,835.00
|
|
|
|
|
|
Bidder Info
|
Bid Amount
|
|
|
SAK Construction, LLC
103 N. Cool Springs Road
O'Fallon, MO 63366
|
$4,224,512.50
|
|
|
|
|