SAWS News: Tunneling, Trenching To Keep City’s ‘Stuff’ Flowing
Aquifer Beaker

Edwards Aquifer

Aquifer Level 664.9'
12/11/17 - Official

The Edwards aquifer and its catchment area in the San Antonio region is about 8,000 square miles and includes all or part of 13 counties in south-central Texas.

Learn More »


image

Year-Round Watering Hours

Watering with an irrigation system or sprinkler is allowed any day of the week before 11 a.m. or after 7 p.m.

Learn More »


Close

Aquifer Level 664.9 | Year-Round Watering Hours

Login

Pay Your Bill Online

Already Registered? Login Now.

Forgot Your Password?

New User

Register for SAWS eBill

Don't Have An Account? Get Started Now.

Sign Up Now


Close
image

Tunneling, Trenching To Keep City’s ‘Stuff’ Flowing

imageSome tunnels are for trains. Others, for love. But this behemoth, 20 feet beneath The Rim shopping center, serves a need far less lovely than railroads or romance: removing sewage from homes and businesses.

The project — which spans almost 3-1/2 miles along Interstate 10 and will triple the size of the current sewer pipe — resembles a minimining operation. Crews must tunnel through hard limestone and dig cavernous trenches far below the surface. The new pipes will employ gravity to move the sewage, removing three energy-intensive lift stations that must currently pump sewage to treatment plants.

“These lift stations are having a tough time meeting (peak) flows,” said Gail Hamrick-Pigg, SAWS’ engineering director overseeing the project.

The $14 million project is about halfway finished and expected to be complete by August 2018.

Over the next 5 years, SAWS will invest $2 billion to upgrade water and sewer infrastructure citywide to ensure reliable service to our customers. Nearly $1.1 billion is needed to repair key sewer infrastructure to meet U.S. Environmental Protection Agency requirements.

That includes a $35 million project along Salado Creek to replace three miles of sewer pipe. This area, which includes Holbrook Road, is susceptible to sewer overflows caused by heavy rain. A second phase, estimated to cost $38 million, will begin in 2018 to replace another three miles of aging sewers along the creek bed.

Currently, more than 60 sewer-related projects are ongoing or scheduled. To find out more about the sewer work in your neighborhood, visit saws.org/sewer.