notice

SAWS offices and payment centers will be closed Monday, May 25, in observance of the Memorial Day holiday. Help with water and sewer emergencies will continue 24/7 at 210-704-SAWS (704-7297).

Two Holes in One

Twice as “boring,” but twice the power. Two tunnel boring machines completed their months-long underground journeys just hours and a few feet apart in May for SAWS’ massive W-6 sewer replacement project along U.S. Highway 90 and SW Military Drive. The project to replace and upsize a giant sewer main near Joint Base San Antonio-Lackland involves five miles of tunnels, to avoid disrupting traffic and military activity on the surface. Construction is expected to be completed in 2023.