Construction Project Summary

money
Job Number: 25-4010

district
City Council District 10

SAWS is replacing aging water lines that have a history of breaks in several neighborhoods as part of the 2025 Water Main Replacement Project 5. These sites include: E Nottingham Drive, Northridge Drive, Shadylane, and Irvington Drive. Construction sites will involve both alleys and streets with each area noted on the map below. During the project, you may see lane closures, detours, or construction activity on nearby streets. At certain times, we may need to temporarily turn off water service while connecting new lines to the existing system. If service will be affected, we’ll notify customers in advance so that they may plan accordingly.

For questions regarding this project, please contact Byron Gipson at 210-233-2977 or [email protected].

money
Estimated Budget: $1,900,000

date
Approx. Timeframe:
10 Months (First Quarter of 2026)

Construction Project Map

utility work ahead


Construction Set to Begin This Year

February 20, 2026

Set to begin this year, 2025 Water Main Replacement Project 5 is a part of the Water Main Replacement Program. The program is a water stewardship initiative and focuses on reducing main breaks in our system.


SAWS Shares Water Line Replacement Plans

February 10, 2026

SAWS staff hosted a meeting at the Tobin Library to discuss the upcoming water infrastructure project.

Set to begin in May 2026, this project installs 881 feet of water main – a little over the length of 1 Tower of the Americas!

During the presentation, SAWS outlined key details including project timeline, process of construction, traffic control plans, and what customers should expect when the project begins.

Towards the end of the meeting, residents had the opportunity to ask questions about how the work may affect their homes and neighborhood streets.


Project Update

Do you have a question about the 2025 Water Main Replacement Project 5 in your area? Join SAWS and contractors at a community meeting.

SAWS will be hosting a community meeting for District 10 residents affected by the 2025 Water Main Replacement Project 5. Learn more about the construction process and have your questions answered by SAWS staff and contractors.

Tuesday, February 3, 2026
Tobin Library – Oakwell – 4134 Harry Wurzbach, SA, TX 78209
6:00 PM – 7:00 PM