Construction Project Summary
|
|
|
|
SAWS is replacing aging water lines that have a history of breaks in several neighborhoods as part of the 2025 Water Main Replacement Project 5 Oak Park Northwood Terrell Heights. These sites include: E Nottingham Drive, Northridge Drive, Shadylane, and Irvington Drive. Construction sites will involve both alleys and streets with each area noted on the map below. During the project, you may see lane closures, detours, or construction activity on nearby streets. At certain times, we may need to temporarily turn off water service while connecting new lines to the existing system. If service will be affected, we’ll notify customers in advance so that they may plan accordingly.
For questions regarding this project, please contact Byron Gipson at 210-233-2977 or [email protected].
|
|
|
|
Construction Project Map

Project Update
Project Will Be Presented to SAWS Board Next Month
April 10, 2026
The 2025 Water Main Replacement Project for Oak Park Northwood Terrell Heights will go to the SAWS Board in May. After the presentation, SAWS will share more details and updated timelines.
Project Update
Construction project will soon go to SAWS Board.
March 27, 2026
The 2025 Water Main Replacement Project 5 Oak Park Northwood Terrell Heights will be going to SAWS Board in May 2026. This project is scheduled to begin in the 1st quarter of 2026.
Project Update
Water Stewardship Remains a Top Priority at SAWS.
March 10, 2026
The 2025 Water Main Replacement Project 5 Oak Park Northwood Terrell Heights will install new HDPE water pipes. These upgraded pipes are stronger, last longer, and are designed to prevent leaks. This means less water loss and more reliable service, especially in San Antonio’s shifting soil conditions.
Project Update
Construction Set to Begin This Year
February 20, 2026
Set to begin this year, 2025 Water Main Replacement Project 5 Oak Park Northwood Terrell Heights is a part of the Water Main Replacement Program. The program is a water stewardship initiative and focuses on reducing main breaks in our system.
SAWS Shares Water Line Replacement Plans
February 10, 2026
SAWS staff hosted a meeting at the Tobin Library to discuss the upcoming water infrastructure project.
Set to begin in May 2026, this project installs 881 feet of water main – a little over the length of 1 Tower of the Americas!
During the presentation, SAWS outlined key details including project timeline, process of construction, traffic control plans, and what customers should expect when the project begins.
Towards the end of the meeting, residents had the opportunity to ask questions about how the work may affect their homes and neighborhood streets.
Project Update
Do you have a question about the 2025 Water Main Replacement Project 5 Oak Park Northwood Terrell Heights in your area? Join SAWS and contractors at a community meeting.
SAWS will be hosting a community meeting for District 10 residents affected by the 2025 Water Main Replacement Project 5 Oak Park Northwood Terrell Heights. Learn more about the construction process and have your questions answered by SAWS staff and contractors.
Tuesday, February 3, 2026
Tobin Library – Oakwell – 4134 Harry Wurzbach, SA, TX 78209
6:00 PM – 7:00 PM