Construction Project Summary
|
|
|
|
SAWS is replacing older water mains that have experienced frequent breaks. As part of the 2023 Water Main Replacement Project 4, construction will take place at two locations: Camden Street and Euclid Avenue.
Camden Street: Installation will be along Camden Street from the intersection of Seymour Street to N. St. Mary’s Street
Euclid Avenue: Installation will be along E. Euclid Ave from the intersection of N. Main Ave. to east of the intersection with McCullough Ave.
We will employ traffic control to minimize disturbances, but you may see detours and lane closures in work areas as lines are being replaced. At times, we may need to temporarily shut off water service to connect new lines to the existing system. If your service will be affected, we’ll notify you in advance.
For questions regarding this project, please contact Cecilia Picazo at 210-233-3750 or [email protected].
|
|
|
|
Construction Project Map

Project Update
Do you have a question about the 2023 Water Main Replacement Project 4 – Camden & Euclid Sites in your area? Join SAWS and contractors at a neighborhood meeting.
SAWS will be hosting a community meeting for District 1 residents affected by the 2023 Water Main Replacement Project 4 – Camden & Euclid Sites. Learn more about the construction process and have your questions answered by SAWS staff and contractors.
Tuesday, September 22, 2026
Central Library – 600 Soledad Street, San Antonio, TX 78205
6:00 PM – 7:00 PM