Construction Project Summary

money
Job Number: 23-4005

district
City Council District 1

SAWS is replacing aging water mains that have experienced frequent breaks. The 2023 Water Main Replacement Project 4 includes three construction sites, one of which is located on E. Hildebrand Avenue.

E Hildebrand Site: Installation will be along Hildebrand Ave and Old Hildebrand Ave from the intersection of McCullough Ave to Devine Road.

We will employ traffic control to minimize disturbances, but you may see detours and lane closures in work areas as lines are being replaced. At times, we may need to temporarily shut off water service to connect new lines to the existing system. If your service will be affected, we’ll notify you in advance.

For questions regarding this project, please contact Cecilia Picazo at 210-233-3750 or [email protected].

money
Estimated Budget: $11,300,000
*Budget amount covers all project sites

date
Approx. Timeframe:
October 2026 – March 2027

Project Reference: 2023 Water Main Replacement Project 4

Construction Project Map

utility work ahead


Project Update

What to Expect Before Construction Begins

October 1, 2026

Customers may see activity in the area beginning October 1, 2026, as crews prepare for construction. This work will include installing project signs, marking underground utilities, and setting up electronic message boards to help keep the community informed.

Plan ahead, since temporary street closures may affect your commute. Electronic message signs will be posted in various areas in early October to provide advance notice with links for information or project updates.

Lane closures will start in late October as crews begin locating underground utilities. Construction is anticipated to begin on October 26, 2026. Once work starts, portions of Hildebrand will be completely closed 24 hours a day, 7 days a week.

The map at the top of the webpage shows the planned construction phases, including when and where full road closures will occur, so residents and businesses can better prepare for work in their area.


Project Update

SAWS Shares Water Line Replacement Plans

September 21, 2026

SAWS staff hosted a meeting with residents and businesses from District 1 at the SAWS Customer Service Building to provide an update on the upcoming water infrastructure project that was approved by the SAWS Board of Trustees on Sept. 1.

Set to begin October 2026, this project replaces 4,600 feet of water main – a little over the length of six Towers of the Americas!

During the presentation, SAWS shared information about the project schedule, upcoming construction activities, contractor information, and what residents can expect in coming months. Attendees asked questions about how the work may affect their homes, neighborhood streets, and traffic in the area. District 1 Councilwoman Dr. Sukh Kaur also attended the meeting and shared information about construction activities and traffic impacts. Continue to visit this site for detailed, up-to-date traffic maps.

 

Community Meeting Presentation

community meetingconstruction


Project Update

Learn What’s Ahead for the E Hildebrand Water Main Replacement

September 4, 2026

SAWS Board has approved the E Hildebrand Water Main Replacement Project. Join us at an upcoming community meeting to learn about the construction schedule, what to expect during the project, and how it may affect your neighborhood.

Thursday, September 17, 2026

SAWS Headquarters Customer Center Building (Tower 2) – 2800 US-281 N, San Antonio, TX 78212
Room CR-C145

6:00 PM – 7:00 PM


Project Update

Water Main Replacement Project Going to SAWS Board

August 21, 2026

The 2023 Water Main Replacement Project 4 – E Hildebrand Site will be going to SAWS Board in September 2026. Additional details and timeline regarding the project will be shared when they become available.


Project Update

Do you have a question about the 2023 Water Main Replacement Project 4 – E Hildebrand Site in your area? Join SAWS and contractors at a neighborhood meeting.

SAWS will be hosting a community meeting for District 1 residents affected by the 2023 Water Main Replacement Project 4 – E Hildebrand Site. Learn more about the construction process and have your questions answered by SAWS staff and contractors.

Thursday, September 17, 2026

SAWS Headquarters Customer Center Building (Tower 2) – 2800 US-281 N, San Antonio, TX 78212
Room CR-C145

6:00 PM – 7:00 PM