SAWS is replacing old water pipes in your neighborhood. Work will take place along the City of San Antonio right of way in the University Park Neighborhood Association area. We will relocate existing water pipes and meters from the alley to the street.

Traffic control will be set up to help keep everyone safe. While crews are working, you may see temporary lane closures or short detours in the area.

For questions regarding this project, please contact Cecilia Picazo at 210-233-3750 or [email protected].

money
Estimated Budget: $8,700,000

date
Approx. Timeframe:
September 2027 (2 years)

Construction Project Map

utility work ahead


Project Update

SAWS Shares Water Line Installation Plans

June 10, 2026

SAWS staff hosted a meeting at Memorial Branch Library to discuss the upcoming water infrastructure project.

Set to begin September 2027, this project replaces 10,160 feet of water main – a little under the length of 14 Towers of the Americas!

During the presentation, SAWS outlined key details including project timeline, process of construction, and what customers should expect when the project begins.

Towards the end of the meeting, residents had the opportunity to ask questions related to right of entry and pipe installation.

 

Community Meeting Presentation

community meetingcommunity meeting


Project Update

Do you have a question about the University Park Water Main Replacement Project in your area? Join SAWS at a community meeting.

SAWS will be hosting a community meeting for District 7 residents affected by the University Park Water Main Replacement Project. Learn more about the construction process and have your questions answered by SAWS staff.

Monday, June 1, 2026
Memorial Branch Library – 3222 Culebra Road, San Antonio, TX 78228
6:00 PM-7:00 PM


Right of Entry

San Antonio Water System (SAWS) and its contractors and subcontractors shall have right to enter upon the property listed above to perform reconnection of a new waterline service lateral to be reconnected to a new water main located within the street right-of-way. At the time of construction award SAWS will engage the contractor to perform the work, and the contractor will be required to reasonably restore any disturbed areas. The undersigned acknowledges that they will look to the contractor regarding such restoration work. The contractor shall make reasonable efforts to provide prior notice to undersigned of the dates and anticipated durations of the entry to perform the work.

Owner

Name(Required)
Owner/Authorized Designee