SAWS is replacing breakage-prone water pipes. Construction will be located within the southern end of the Oak Park Northwood neighborhood, from Northridge Drive to Eisenhauer Road and Greenwich Boulevard to Chevy Chase Drive.
During the project, you may see lane closures, detours, or construction activity on nearby streets.
At certain times, we may need to temporarily turn off water service while connecting new lines to the existing system. If service will be affected, we’ll notify customers in advance so that they may plan accordingly.
For questions regarding this project, please contact Byron Gipson at 210-233-2977 or [email protected].
|
|
|
|
Construction Project Map

Streets impacted:
- E Nottingham Dr – From Greenwich Blvd to Chevy Chase Blvd
- E Nottingham Dr (alley between Tophill Rd & E Nottingham Dr) – From Greenwich Blvd to Chevy Chase Blvd
- Robinhood Pl (alley between E Nottingham Dr & Robinhood Pl) – From Greenwich Blvd to Chevy Chase
- Kenilworth Blvd – From Northridge Dr to E Nottingham Dr (alley)
- South Kenilworth Blvd – From Robinhood Pl (alley) to Robinhood Pl
- South Kenilworth Blvd – From Robinhood Pl to Eisenhauer Rd
- Calumet Pl (alley between Robinhood Pl & Calumet Pl) – From Greenwich Blvd to Kenilworth Blvd
- Ridgehaven Pl (alley between Calumet Pl & Ridgehaven Pl) – From Greenwich Blvd to Kenilworth Blvd
- Brightwood Pl (alley between Ridgehaven Pl & Brightwood Pl) – From Greenwich Blvd to Kenilworth Blvd
Project Update
SAWS Shares Water Line Installation Plans
May 14, 2025
SAWS staff hosted a meeting at the Tobin Library to discuss the upcoming water infrastructure project.
Set to begin January 2027, this project replaces 9,900 feet of water main – a little over the length of 13 Towers of the Americas!
During the presentation, the consultant outlined key details including project timeline, process of construction, traffic control plans, and what customers should expect when the project begins.
Towards the end of the meeting, residents had the opportunity to ask questions related to parking and access to driveways.
Community Meeting Presentation


Project Update
Do you have a question about the Oak Park Northwood Water Main Replacement Project in your area? Join SAWS and contractors at a community meeting.
SAWS will be hosting a community meeting for District 10 residents affected by the Oak Park Northwood Water Main Replacement Project. Learn more about the construction process and have your questions answered by SAWS staff and contractors.
Tuesday, May 12, 2026
Tobin Library at Oakwell – 4134 Harry Wurzbach Rd, San Antonio, TX 78209
6:00 PM-7:00 PM